Kuwait National Rail Road Project (KNRR)

The project client, Kuwait’s Public Authority for Roads and Land Transportation (Part), through the Kuwait Authority for Partnership Projects (Kapp), issued a request for proposals. The original closing date was 21 February. The deadline has been extended to 11 July.


Project Name: Kuwait National Rail Road

Country: Kuwait

Brief Overview:

1.     Project Ref No: SPR791-K

2.     Length: 265km, including passenger and freight line

3.     Track: Double

4.     Rail Speed: 120 km/h regional speed & 200 km/h high speed

5.     Estimated cost: 2$ billion

6. Official Route: Kuwait to Muscat via KSA, Bahrain, and Qatar.

7.     Project Stage: New Tender

Project/Tender Owner:

1. Ministry of Communications Complex, Jamal Abdul Naseer Street, Shuwaikh, P.O Box 318, Safat 11111, Kuwait.

2.     Contact No: +96524819033, Fax: +96524847058,

3.     Website: http://www.moc.kw

4.     Trade Category: Publick Transportation Projects

KeyPoints:

1.    Two New Lines: 1st 111km stretch from KSA border at Nuwaiseeb to Kuwait City, superior service with 6 passenger service a day.

2.     Train required: 10 trains with a speed of 220 km/h. A freight line will continue to Boubyan Port with only standard services.

3.     Transport Model: Parsons Brinckerhoff Group and local Kuwait Technical Bureau

4.     Master Plan Consultant: Ingenieria y Consultoria S.A


Comments

Popular posts from this blog

Bahrain announces 220 kV & 66 kV Transmission Development Project – Phase 2

The 220 kV & 66 kV Transmission Development project in Bahrain began in 2012 and is ongoing. The project aims to enhance the transmission infrastructure in Bahrain and has already completed its initial phase from 2012-2016. This project is a significant step towards ensuring reliable and efficient power transmission in Bahrain. With ongoing efforts to enhance the transmission infrastructure, Bahrain is poised to become a regional leader regarding power transmission capabilities. In March 2019, the Electricity & Water Authority (EWA) received proposals from contractors for 14 substations as part of the ongoing project. Later that year, an additional substation was added to the project. By 2024, bidders were shortlisted for the 66kV substation package, which includes the design, supply, installation, testing, commissioning, and maintenance of fourteen 66/11kV substations on a lump sum turnkey basis. This demonstrates the commitment and progress towards the completion of the proje...

Inside the Erada Centre Treatment and Rehabilitation Project

  The Era da Centre Treatment and Rehabilitation Project is in Umm Eselay, Dubai, UAE. This project is vital to the community as it aims to provide essential care and treatment. However, It is commendable that the organization has taken up the responsibility to provide such services and develop healthcare infrastructure. As of March 6, 2024, the Erada Centre Treatment and Rehabilitation Project is progressing well. Moreover, Th RFP for the main construction contract was issued on January 16, 2024, and the bid submission deadline was February 15, 2024. The Dubai Municipality Projects Department awards the main construction contract by the second quarter of 2024. Construction will begin following the awarding of the contract. Also, The project is finalizing the bidding and awarding phase, with preparations underway for the commencement of construction activities. To provide an overview of the Erada Centre Treatment and Rehabilitation Project's, the following milestones have been ac...

Aramco General Engineering Services Plus (GES+) Contract Renewal

Aramco's general engineering services contract renewal of Worley's GES+ for an additional five years is a testament to a good relationship between the two companies. This demonstrates Worley's services' quality and reliability and commitment to providing top-notch engineering solutions. Undoubtedly, Worley will continue to exceed expectations and deliver exceptional results to Aramco. Worley has renewed its five-year GES+ contract with Aramco General Engineering Services to provide project management and engineering services. It includes various gas, oil, and energy infrastructure projects in Saudi Arabia. The company will prioritize local talent development and in-kingdom engineering capabilities. Also, Chris Ashton, Worley CEO, expressed his pleasure in continuing the long-term relationship with Aramco and expanding Worley. Aramco and Worley's five-year contract renewal with the potential for extension was announced in Year 1. The company has committed to deliveri...